The entire project area had been the location of intense fighting and bombing during the Second World War, which on its own, in order to guarantee the safe execution of the dredging works, proved to be a vast undertaking. However, despite this anticipated challenge as well as some exceptional events, such as working during a pandemic (COVID-19) and a difficult period of cold and ice, the ambitious project was completed on time and was handed over to the Maritime Office in Szczecin in the spring of 2022.
Design and engineering
The project was executed in a design and construct format, encompassing a wide array of design tasks, such as the fairway dredge design, two artificial islands with jetties, rock revetments, sheet piling, cable alterations, navigational aids and the implementation of a hydrometeo and Real Time Kinematic (RTK) system.Design work in Poland is strictly regulated, permitting only certified designers to endorse design documentation. To handle the diverse range of design tasks and adhere to Polish design regulations, a consortium of Polish and Belgium design consultants was engaged. The design consortium together with designers of both dredging contractors worked together closely to complete the design.
The fairway remained open for other vessels during the marine works. This required special attention to ensure safe dredging operations, taking into account the dredging fleet deployed, without posing an obstruction to vessels calling at port. Nautical studies were performed, creating a framework of safe passing manoeuvres for other vessels during different dredging operations (dredging, sailing loaded and sailing empty). The nautical study along with clear communication with Vessel Traffic Services (VTS) and local pilots ensured safe vessel procedures and minimised delays in the dredging operations.
The dredged material was used to create two artificial islands, with diameters of approximately 1.25 kilometres and 1.8 kilometres respectively. In the north is a nature island with no infrastructure other than a jetty required to access the island for inspections. The southern “doughnut-shaped” island will serve as a reclamation area for future maintenance dredging on the fairway. Both artificial islands are located within the Szczecin Lagoon. The original bed level at the island locations was about -5 to -6 metres. Soil investigation campaigns revealed layers of soft soils, with thicknesses varying between 1 to 8 metres. The presence of these soft soil layers greatly influenced the design and construction of the artificial islands. A rubble mound bund with steep slopes proved to be unstable. Therefore, the design was adopted to ensure geotechnical stability of the works and optimise the volume of rock required for construction.
The first step in the island construction was the installation of the sand foundation. The elevation of the foundation layer varies from -2 to -3 metres, depending on the hydraulic loading by waves after the island’s completion. The foundation layers were installed by means of a spreader pontoon and followed by a consolidation period. The duration of the consolidation period varied based on the local subsoil conditions. During the second construction step, a sand bund was created reaching above water. Once dry land was formed, Cone Penetration Tests (CPT’s) were performed. Over a hundred CPT’s were conducted on both artificial islands to confirm the soil models used for calculating consolidation periods and to determine the degree of consolidation of the soft soil layers. Based on the CPT data, a second consolidation period was determined for every location along the island to ensure sufficient consolidation of the soft soil layer and increase the strength, enabling a safe raising of the reclamation levels to the design levels, up to +5 metres.
The construction sequencing of both islands, determined by the geotechnical stability and associated consolidation periods, is visualised with four satellite images shown in Figures 1A-D. Figure 1A, taken in October 2020, shows the submerged sand foundation layer at both islands. On the southern island, the western sector of the island was constructed above water first, since this part of the island required the longest consolidation period between the first and second above water reclamation step. At the northern island, the above water operations commenced.